Current Capital Projects

As part of a long-range master plan, Fiscal Year 2018-2019 will see the City continue to reinvest in its infrastructure, particularly in the area of roadways, parks, and streetscapes as described below:

Freeway Frontage Landscape 

Construction of new landscaping along the Southwest Quadrant of the Lindero Freeway Interchange has been completed and is currently in the maintenance period.  The project will be closed out and accepted by the City in early March.  From there, we can all watch together as the trees grow to maturity over the next few years!

Westlake Village Community Park

Is currently closed due to fire damage.Once a deep cleaning of the fields and some needed repairs are finalized, the Community Park will reopen. Additional work will be needed to restore plants, fencing, and other elements impacted by the fire for the next few months. Netting to protect the picnic area from fly balls is anticipated for late 2018 to early 2019 as well as a formalized trail to the skate park.

Annual Street Resurfacing Program/ ADA Improvements

The Annual Street Resurfacing Program includes grinding and new asphalt pavement along Russell Ranch Road and various intermittent residential streets in Canyon Oaks, Three Springs and Rustic Oak neighborhoods as well as Corsa Ave. and La Baya Drive.  Slurry seal coating will occur on Via Rocas and Via Colinas.  In addition, a new rapid flashing beacon crosswalk will be installed on Russell Ranch (near the entrance to the Target portion of The Shoppes at Westlake Village).


Update: Slurry seal is scheduled for Saturday work in mid-February on Via Rocas and the portion of Via Colinas between Via Rocas and Lindero Canyon Road, and weekdays in mid-February for Sterling Center, Canterhill, Glenbridge and Ridgeford Drive.  The planned grinding and paving work is now scheduled to commence in early February, beginning in Canyon Oaks and Three Springs neighborhoods, followed by Saturday work for paving on Corsa Avenue, La Baya, Via Colinas between Thousand Oaks Blvd and Via Rocas, and Portola Court.  Pavement patch repair work on Lindero Canyon Road north of Whim and on Kentfield Drive in First Neighborhood and Foxfield Drive in the Westlake Trails Neighborhood will also be performed in mid-February.  Paving on Russell Ranch Road is scheduled at the end of February.


Lindero Walkway and Beautification Project

This project began in September 2018 and when complete will include a meandering sidewalk, water efficient vines and plants, new trees, and an environmental bio-swale to help clean storm water that eventually flows to the ocean. For more information including renderings please click here. Work continues on Phase 1  from Agoura Road to Rustic Oak Lane. Work will begin on November 1 to position on-site fencing for Phase 2 from Rustic Oak Lane to Fox field Drive. There are no traffic impacts expected during the week of October 29 to November 2. Pedestrian pathways will be closed during the construction.